Implementing MPS in a live ERP for contract manufacturers (the phase-2 playbook I actually use)
- John Hannan

- Jan 16, 2024
- 6 min read

If you build to print for multiple OEMs—laser/punch, form, weld, finish, assemble—you already know why Master Production Scheduling (MPS) matters. Contract manufacturing runs on other people’s forecasts, late ECOs, long-lead metals and coatings, and outside processing you don’t fully control. Turning that noise into one weekly, believable plan is the job.
This post is how I lead an already-live contract manufacturer from “we need MPS” to “we run MPS every week and trust the dates.” The team has the knowledge; I supply the method, guardrails, and artifacts. We start by proving what your ERP can do natively. If it fits, we implement there. If it doesn’t, I’ll run a focused selection for a third-party planning engine and then implement that. Either way, the cadence and outcomes are the same.
The reality check (specific to contract mfg)
MPS is not “more MRP.” MRP explodes components. MPS decides what you build when—finished goods, sub-assemblies, or families—then lets MRP calculate what to buy and kit.
You’re ready to add MPS when these are true (or we fix them fast as part of the work):
Routings reflect the floor - Setup/queue/move times for laser, press brake, weld cells, and the powder-coat line—not placeholders.
Outside operations are real objects - Plating, heat treat, and specialty coatings modeled as operations tied to POs with vendor calendars and transit days.
Lead times + vendor acks circulate - Buyers get promise dates back into the plan.
Inventory accuracy is boring - Cycle counting on rails; remnant handling and UoM conversions for coil/sheet/lengths tested.
Demand is structured - Forecasts + firm releases (EDI 830/862/866 or portal) by customer/program with clear consumption rules.
Without those, MPS amplifies chaos.
What makes contract-mfg MPS unique (and tricky)
Family vs. variant reality - You often need a planning BOM/family keyed to alloy/gauge/finish to stabilize upstream laser/press brake loads while the last-inch variant (hardware kit, label set) changes late.
Changeover economics - Sequencing by gauge/alloy or powder color reduces changeovers—but you still owe the promise date. MPS must balance both.
Subcontract capacity you don’t own - Bucketed capacity and vendor calendars for plating/powder must be respected or your published dates are fiction.
Mixed turnkey/consigned supply - Different programs run both, and your plan must peg cleanly either way.
Label/pack/ASN compliance - Finished-goods dates are meaningless if pack-out, labeling, and ASN timing aren’t in the routing or buffer.
How I run phase-2 MPS (two lanes, same destination)
Lane A — Make your ERP’s native MPS sing - If your system can handle forecast consumption, time fences, RCCP/finite constraints, subcontract operations, and long-lead pegging, we implement there.
Lane B — Add a planning engine (APS/MPS) - If native planning can’t model families, multi-site constraints, or subcontract networks, we prove and implement a third-party tool. Selection is light and evidence-based, not “demo theater.”
A recent field pattern (contract manufacturer)
Mid-size U.S. contract manufacturer making fabricated and coated metal assemblies for multiple OEMs. Two OEMs send rolling forecasts plus firm weekly releases. Long-lead metals; color-change pain on the powder line; plating is subcontracted with a 3-day ship-out/ship-back loop. The team “planned” in Excel; buyers were drowning in expedites.
What we did:
Forecast consumption by program/customer - Backward/forward windows; partial-consumption enabled so late firm orders didn’t double count the forecast.
Fences & release horizon - Demand Time Fence (DTF) to freeze dates/qtys near-term; Planning Time Fence (PTF) to limit system reschedules; auto-firm planned orders as they crossed the horizon.
Family-level MPS - Planning items by alloy/gauge/finish stabilized upstream loads; variant-specific hardware/labels driven late via phantom/optional components.
Outside-ops modeled as ops - Subcontract plating tied to operation-linked POs with vendor calendars, carrier transit, and WIP backflush on return.
RCCP then finite - Rough-cut capacity at family level (laser/press brake/powder), then finite constraints with real setup/queue for the powder line.
Buyers’ workbench + safety time - Long-lead metals used safety time (not stock) and MOQs/multiples; buyers accepted/overrode suggestions only after vendor acknowledgements.
One weekly cadence - Monday demand, Tuesday RCCP/finite rough-in, Wednesday buys/acks, Thursday firm & publish, Friday metrics & ECO window.
What changed within 6 cycles - expedite rate fell ~30%, order moves inside DTF dropped materially (plan stability), and OTTP on firm releases reached the low-to-mid 90s—without hiring planners. That’s typical when the mechanics are wired to your realities.
The 10-Day Capability & Readiness Sprint (always step one)
You get:
Fit/gap map of native MPS vs. your contract-mfg needs (severity-coded).
Coverage templates by family/customer class: DTF/PTF, release horizons, safety time vs. stock, order modifiers (MOQ, multiples).
Outside-ops model - routing pattern, subcontract PO template, labels/travelers, WIP accounting.
Forecast consumption design - classes, windows, partial consumption edge cases.
Pegging health check end-to-end - sales line → MPS item → job → PO/subcontract, including consigned vs. turnkey.
KPI baseline - OTTP, plan stability (order moves/week), expedite rate, late vendor acks, past-due ops, shortage at job start.
This evidence decides Lane A vs. Lane B.
Lane A: Implement MPS inside your ERP
Coverage groups & fences
DTF/PTF per family & customer class
Release horizon that auto-firms crossing planned orders
Planners use firm planned orders to stop plan nervousness
Forecast consumption that actually consumes
Backward/forward windows per OEM
Partial consumption (when firm orders cover some—but not all—of a bucket)
Tests for late releases, de-releases, and cancellations
Capacity: RCCP → finite
Rate-based RCCP at family level (laser, press brake, powder)
Finite rules on constraints (powder booth/oven, brake tonnage limits, weld cells); validate with a week of shop feedback
Outside processing
Operation-linked POs with vendor calendars and transit buffers
Bucketed subcontract capacity if the supplier won’t schedule discrete slots
Quality holds block downstream ops and trigger replans
Long-lead procurement
Safety time for unreliable supply; safety stock where consumption variability dominates
MOQ/multiples/min-max tuned by item class
Buyers’ workbench becomes the single place to act on messages—
ECO governance
Versioned BOMs/routings with effectivity dates
Where-used before approval; ECO window near DTF to prevent ripple damage
Keep configuration rules in one system (PLM/CPQ/ERP) and respect effectivity
Dashboards & exceptions
Late supply, negative on-hand, past-due ops, ECO pending, late acks
Expedite/de-expedite/cancel messages prioritized by severity, not alphabetically
Weekly MPS cadence
Mon - load demand & run consumption
Tue - RCCP + finite rough-in; sanity check constraints
Wed - process long-lead buys; collect vendor acks
Thu - convert planned→firm inside horizon; publish schedule
Fri - KPIs + ECO window; lock changes inside fences unless approved
Pilot → scale
Start with 1–2 OEM programs and 2–3 families; once metrics hold, copy coverage groups across product lines with minimal tweaks.
Lane B: When native MPS won’t bend (add a planning engine)
Lightweight proof, not theater:
Scripted scenarios (your data) - forecast consumption by program, DTF/PTF behavior, family planning, subcontract ops with transit, long-lead pegging, ECO effectivity, mixed turnkey/consigned.
Back test 8–13 weeks - compare suggested releases/buys/load to what actually happened.
Integration sketch - items/BOMs/routings/calendars in; demand/acks/receipts/completions round-trip; frequency and owners.
Pilot cut - small scope, real constraints; prove stability and OTTP before rollout.
Then we implement and lock the same weekly discipline.
Contract-mfg pitfalls I fix again and again
Two plans (ERP vs. Excel) - Solution: one published weekly plan; spreadsheets for analysis only.
Forecasts never consume - Solution: correct classes/windows; test partial-consumption edge cases.
Unlimited rescheduling - Solution: DTF/PTF + firming rules + release horizon.
Long-lead left in spreadsheets - Solution: pegged buys from MPS item down; safety time for metals and coatings.
Outside ops as an afterthought - Solution: operation-linked POs with calendars, labels, WIP accounting.
Variant/item chaos - Solution: family planning and clear identifier strategy (phantoms/optionals) to prevent component whipsaw.
“Pretty Gantt, ugly math” - Solution: calibrate calendars, setup/queue, and validate with the floor before promising dates.
KPIs that keep us honest
On-Time to Promise (OTTP) on firm releases
Plan stability (order moves/week inside DTF)
Expedite rate and premium freight incidents
Late vendor acknowledgements and promise-date variance
Schedule adherence at constraint work centers (powder, brake, weld)
Shortage rate at job start
If those trend the right way inside 4–8 cycles, MPS is working. If not, the exception dashboards tell us where the plan is lying.
What I deliver so your team can run it without me
MPS coverage templates (fences, horizons, safety, order mods) by family and customer class
Buyers’/planners’ workbenches with tuned exception thresholds
Outside-ops playbook (routing patterns, subcontract PO templates, label/traveler examples, WIP accounting)
Data kits (items/BOMs/routings/lead times) and vendor-ack handling
CRP/UAT scripts that stress consumption, fences, subcontract, alternates, ECOs
Weekly MPS deck + live dashboards wired to your data
Cutover runbook (convert planned→firm, re-peg buys, supplier comms)
Your planners keep the keys. My job is to make the cadence stick.
If you’re a contract manufacturer living on OEM releases and outside processing—and your dates still feel like suggestions—this is fixable. I’m happy to share the exact templates and scripts I used on the project described above (de-identified, but real). If the approach is useful, you’ll reach out.











